South Dakota: data center, solar, wind and pipeline rules and hearings

Informational only, not legal advice. Summaries of official .gov sources as of the dates shown; they may be incomplete, out of date or wrong. Do not rely on them. Always check the issuing agency and its meeting agendas before acting.

2 cited records from official .gov sources. 1 of 2 listed places covered. Last checked 2026-11-26.

Coverage by place

PlaceCoverageLast checkedNote
South DakotaCovered2026-11-26State legislation only (2026 SB 239). Counties and cities are listed separately; state siting rules not reviewed yet.
City of Rapid City, South DakotaNot covered2026-11-26Not reviewed from an official .gov source yet.

"Not covered" means we have not cited this place from an official .gov source yet. It does not mean the place has no hearings, moratoria or rules.

Cited records

South Dakota

South Dakota: 2026 SB 239 tax rebate bill (data centers listed) failed in the Senate Tax break · data centers, wind, power generation · as of 2026-02-24

2026 Senate Bill 239 would have modified the reinvestment payment program. Senate State Affairs amended it and passed it 6-3 on Feb. 18, 2026. It failed on the Senate floor 17-16 on Feb. 23 and failed again on reconsideration 16-17 on Feb. 24, 2026.

Official source: 2026 Senate Bill 239 (reinvestment payment program) · South Dakota Legislature · 2026 SB 239 bill history · retrieved 2026-11-26 · last checked 2026-11-26
South Dakota: SB 239 amendment listed data centers and wind facilities as projects Tax break · data centers, wind, power generation · as of 2026-02-18

The committee amendment (239B) defined a project as a new or expanded facility costing more than $20 million (or equipment upgrades over $2 million) and listed data centers, power generation and transmission facilities, and wind energy facilities among eligible projects. The bill did not pass.

Official source: Senate State Affairs committee report on SB 239, amendment 239B (PDF) · South Dakota Legislature · Amendment 239B, definition of "project" · retrieved 2026-11-26 · last checked 2026-11-26

Get free South Dakota alerts →

FAQ

Which South Dakota places are covered?

Covered with cited .gov records: South Dakota. Each place shows its own last-checked date.

Which South Dakota places are not covered?

Not covered yet: City of Rapid City, South Dakota. "Not covered" does not mean there are no rules or hearings there.

How do I get alerts for South Dakota?

Pick South Dakota in the free Large-project rule watch sign-up and confirm by email (double opt-in). Alerts are in test mode now, so no alert emails go out yet. Unsubscribe any time with one click.

Is this legal advice?

No. It is informational only. Confirm every item with the issuing agency before acting.